CITY OF SANTA FE: Orange Barrel Report for the Week of October 19, 2020

Construction

City of Santa Fe issued the following announcement on Oct. 16.

New:

High 5 networks: Installing a new fiber line for Comcast open trench excavation. Agua Fria will be closed at Defouri. Traffic detours will be in place at Defouri to Alameda to S. Guadalupe Street. Work will begin 10-14-20 to 10-30-20. Contact Kody Keelin at 505- 231-4987 for any questions. 

Rodgers Plumbing and Heating: Installing a new water main line on Paseo De Peralta at Old Taos Hwy beginning 9-28-20 to 10-20-20. Double lane shift for traffic control will be put in place on Paseo De Peralta from Griffin Street to Bishops Lodge Rd. Please seek alternative route. Contact Kody Keelin at 505-231-4987 for any questions.

On Going:

Kassam Construction: Installing a new median, dividing Richards Ave. in front of the Home Depot. Lane shifts will be in place from 9-30-20 to 10-20-20, and traffic control will remain in place for the remainder of the project. Date TBD. Contact Santiago Gonzales at 505-975-1391 for any questions.

GM Emulsion: Installing turn lanes, and widening Rufina St. at Camino Del Griego. Lane shifts, and detours will be in place. Work is ongoing, but may have delays through 12-31-20. Contact Angelo Gonzales at 505-471-9981 for any questions.

GM Emulsion: Construction of Rail Trail from Alta Vista Street to Pen Road and a trail connection at Monterey Drive to the Rail Trail. Work will begin 5-26-20 to 10-31-20. Flaggers and *lane shifts will be in place. Contact Jeremy Martinez at 505-955-6931 for any questions.

GME General: Removing and resetting the sidewalk bricks, and installing sidewalks and culverts along Lincoln Ave to W. Palace, and Washington Ave to W. Palace. Work is scheduled to begin 8-5-20 to 10-23-20. Contact Angelo Gonzales at 505-471-9981 for any questions.

EMCO: Construction of bike lanes on both sides of Old Santa Fe Trail from E Zia Road south to City limits. Work will begin 5-26-20 to 10-31-20. Flaggers and lane shifts will be in place. Contact Jeremy Martinez at 505-955-6931 for any questions.

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS