Orange Barrel Report for the Week of September 26, 2021

Orange barrel report

Contributed photo

Contributed photo

Weekly Road Maintenance and Construction Updates

Orange Barrel Report for the Week of 
September 26, 2021
 

New:
 
EMCO: Will be re-paving Acequia Borrada and Acequia Borrada West. Work is scheduled to begin 9-27-2021 thru 10-1-2021. Flagger operation will be in place, expect delays. Contact Mark Brooks at 505-955-2404 with any questions.
 
GM Emulsion: Will be re-paving Camino Carlos Rey from Zia Road to Siringo. Work is scheduled to begin 9-27-2021 thru 10-8-2021. Flaggers and road detours will be in place, expect delays. Contact Mark Brooks 505-955-2404 with any questions. 
 

On Going:
 
Klinger Construction: Will been installing a new curb and gutter on the Old Taos Hwy. Work is scheduled to begin 09-20-2021 thru 10-15-2021. A fence will be set out farther from the work site and have a ten foot wide lane for all North bound traffic. The South bound lane will not be affected by this work. Contact Kody Keelin at 505-231-4987 with any questions.

Facility Build and the City of Santa Fe: Will be installing new restrooms at the Water Street parking lot. The sidewalk on East Water Street will be closed for the demolition of the existing wall starting on 09-06-2021 thru 11-19-2021. Contact Kody Keelin at 505-231-4987 with any questions.
 
Sierra Canyon Construction: Will be adding a Decel Lane at 6581 Cerrillos Rd. Lane shifts will be in place, work is scheduled to begin 08-31-2021 thru 09-30-2021. Contact Teddy Padilla at 505-231-4794 with any questions.
 
Technical Review Corp: Will be repairing a sewer line at 708 E. Palace Ave. Work is scheduled to begin 09-02-2021 thru 09-30-2021. Lane shifts and flaggers will be in place. Contact Teddy Padilla at 505-231-4794 with any questions.
 
Kelly Cable: Will be installing new fiber optic cable overhead and boring. Rodeo road will have be reduced to one lane from Richards Ave to Cerrillos road and continuing on Airport road to Lopez Lane. Work will begin on 08-02-2021 thru 10-30-2021. Contact Kody Keelin at 505-231-4987 with any questions.
 
Kelly Cable: Will be installing new fiber optic cable overhead on Lopez Lane. Lopez Lane will have flagmen from Airport road to Rufina. Work will begin 08-09-2021 thru 10-30-2021. Contact Kody Keelin at 505-231-4987 with any questions.
 
Bradbury Stamm Construction: Will be installing underground utilities at 2068 Galisteo St. work is scheduled to begin 06-28-2021 thru 11-30-2021. Contact Teddy Padilla 505-231-4794, with any questions.
 
Salls Brothers Construction: Will be installing a new turn lane for the Desert Sage Subdivision. Work is scheduled to begin 07-26-2021 thru 10-15-2021. Shoulder work with a lane shift will be in place, watch for flag men and trucks turning. Richards Ave south east of Beckner road. Contact Kody Keelin at 505-231-4987 with any questions.
 
TLC: Will be installing new turn bays on South Meadows Road starting 07-02-2021 thru 10-30-2021. Shoulder work and center median work will be taking place please watch for flag men and trucks turning. Contact Kody Keelin at 505-231-4987 with any questions.
 
Klinger Construction: Single lane closed on Paseo De Peralta for construction From Washington Ave to Old Taos Highway. Traffic control will stay in place for the remainder of the project. Contact Kody Keelin at 505-231-4987 with any questions.

Savannah Saiz
Constituent Services Specialist 
505-955-6048 

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS