CITY OF SANTA FE: Orange Barrel Report for the Week of December 28, 2020

Construction

City of Santa Fe issued the following announcement on Dec. 23.

On Going:

Matrix Builders: Will be installing a water line, and storm drain on Beckner Rd - right next to the V.A. Hospital this Saturday and Sunday 12-19-20 – 12-20-20. The East bound lane will be closed, then starting on Monday 12-21-20 thru 12-25-20 the West bound lane will be closed. The detours will be through Wellness Way. Contact Allen Martinez at 505-690-3265 for any questions

Desert Fox LLC: adding a turn lane on Airport Rd. and Zepol Rd. The bus stop at this address will be removed, and temporarily replaced. There will be sidewalk closures, lane closures, and lane shifts. Expect delays. Work is scheduled to begin 12-7-20 thru 1-4-21. Contact Ali Al Sigar, at 505-892-5400 for any questions.

Klinger Construction: Building a new deceleration lane at 7521 Cerrillos Rd, with curb, gutter, sidewalks, and lane striping. Expect delays as the turning lane to get behind the new Wal-Mart will be blocked off. Work is scheduled to start 11-13-20 thru 1-31-21. Contact Jeffrey Slopek at 505-615-7646 for any questions.

Sub Surface Contracting: Removing and replacing the main water line on Camino Racheros, and Camino Ranchitos, El Caminito and a portion of Camino Del Monte Sol. Work will begin 11-4-20 thru 01-22-21 Contact Jeremey Sanderson (505) 690-1440 for any questions.

Klinger Construction: Single lane closed on Paseo De Peralta for construction From Washington Ave to Old Taos Highway. Traffic control will stay in place for the remainder of the project. Contact Kody Keelin at 505-231-4987 for any questions.

Kassam Construction: Will be finishing up with sidewalks, and drive entrances, and will be placing temporary striping on road. Traffic control will remain in place until striping is done. Contact Santiago Gonzales at 505-975-1391 for any questions.

GM Emulsion: Installing turn lanes, and widening Rufina St. at Camino Del Griego. Lane shifts, and detours will be in place. Work is ongoing, but may have delays through 1-31-21. Contact Angelo Gonzales at 505-471-9981 for any questions.

GM Emulsion: Construction of Rail Trail from Alta Vista Street to Pen Road and a trail connection at Monterey Drive to the Rail Trail. Work will begin 5-26-20 thru 01-30-21. Flaggers and *lane shifts will be in place. Contact Jeremy Martinez at 505-955-6931 for any questions.

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS